Process Step | Date Initiated | Date Completed | Comments |
Received | 10/13/2016 | 10/13/2016 |
|
ODFW Review | 10/14/2016 | 8/8/2017 |
|
WMR Request | 10/14/2016 | 10/19/2016 |
|
Transfer Initial Comment Period | 10/18/2016 | 11/18/2016 |
|
Draft PD Issued | 4/18/2017 | 4/18/2017 |
|
PD Issued | 9/7/2017 | 9/7/2017 |
|
PD Weekly Public Notice | 9/12/2017 | 9/12/2017 |
|
Final Order Issued | 10/23/2017 | 10/23/2017 |
|
Certificate Remaining Issued | 10/23/2017 | |
CERT 93374 ISSUED SUPERSEDES CERT 62160
|
Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
CBU Completeness Review | 7/17/2020 | 7/22/2020 |
|
CBU Received | 7/17/2020 | 7/17/2020 |
|
CBU Due | 10/1/2020 | 10/1/2020 |
|
Certificate Confirming Issued | 7/22/2022 | 7/22/2022 |
|