| Process Step | Date Initiated | Date Completed | Comments |
| Received | 10/21/2016 | 10/21/2016 |
|
| WMR Request | 10/24/2016 | 10/27/2016 |
|
| GW Review Request | 10/24/2016 | 9/8/2017 |
|
| Transfer Initial Comment Period | 10/25/2016 | 11/25/2016 |
|
| Draft PD Issued | 11/2/2017 | 11/2/2017 |
|
| GW Review Request | 1/4/2018 | 1/4/2018 |
|
| PD Issued | 1/17/2018 | 1/17/2018 |
|
| PD Weekly Public Notice | 1/23/2018 | 1/23/2018 |
|
| Final Order Issued | 3/16/2018 | 3/16/2018 |
|
| CBU Received | 10/19/2018 | 10/19/2018 |
|
| Proposed Certificate Mailing | 8/15/2023 | 8/15/2023 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| Certificate Confirming Issued | 11/17/2023 | 11/17/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|