Process Step | Date Initiated | Date Completed | Comments |
Received | 10/24/2016 | 10/24/2016 |
|
WMR Request | 10/27/2016 | 3/14/2017 |
|
GW Review Request | 10/27/2016 | 4/9/2018 |
|
Transfer Initial Comment Period | 11/1/2016 | 12/2/2016 |
|
Deficiency Letter | 5/17/2018 | 8/22/2018 |
|
Draft PD Issued | 9/7/2018 | 10/18/2018 |
|
Deficiency Letter | 10/10/2018 | 10/18/2018 |
Waiting on Report of Ownership
|
News $ Due Letter | 10/23/2018 | 11/13/2018 |
|
PD Issued | 11/19/2018 | 11/19/2018 |
|
PD Weekly Public Notice | 11/20/2018 | 11/20/2018 |
|
Final Order Issued | 1/30/2019 | 1/30/2019 |
|
CBU Received | 4/9/2020 | 4/9/2020 |
|
Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|