| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/1/2016 | 11/1/2016 |
|
| WMR Request | 11/4/2016 | 12/23/2016 |
|
| Transfer Initial Comment Period | 11/8/2016 | 12/9/2016 |
|
| Draft PD Issued | 3/2/2017 | 3/14/2017 |
|
| PD Issued | 4/7/2017 | 4/7/2017 |
|
| PD Weekly Public Notice | 4/11/2017 | 4/11/2017 |
|
| Final Order Issued | 5/17/2017 | 5/17/2017 |
|
| CBU Received | 7/20/2018 | 7/20/2018 |
|
| Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
| Certificate Confirming Issued | 1/3/2019 | 1/3/2019 |
|
| CBU Due | 10/1/2019 | 10/1/2019 |
|