| Process Step | Date Initiated | Date Completed | Comments |
| Received | 10/31/2016 | 10/31/2016 |
|
| GW Review Request | 11/3/2016 | 6/8/2017 |
|
| WMR Request | 11/3/2016 | 11/8/2016 |
|
| Transfer Initial Comment Period | 11/8/2016 | 12/9/2016 |
|
| Draft PD Issued | 9/21/2017 | 9/21/2017 |
|
| PD Issued | 1/17/2018 | 1/17/2018 |
|
| PD Weekly Public Notice | 1/23/2018 | 1/23/2018 |
|
| Final Order Issued | 3/5/2018 | 3/5/2018 |
|
| Certificate Remaining Issued | 3/5/2018 | |
RR Cert 93599 issued superseded Cert 64009
|
| Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
| CBU Completeness Review | 9/18/2020 | 9/22/2020 |
|
| CBU Received | 9/18/2020 | 9/18/2020 |
|
| CBU Due | 10/1/2020 | 10/1/2020 |
|
| Certificate Confirming Issued | 9/16/2022 | 9/16/2022 |
|