| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/28/2016 | 11/28/2016 |
|
| WMR Request | 12/1/2016 | 12/23/2016 |
|
| GW Review Request | 12/1/2016 | 8/23/2017 |
|
| Transfer Initial Comment Period | 12/6/2016 | 1/6/2017 |
|
| Draft PD Issued | 12/13/2017 | 12/13/2017 |
|
| PD Issued | 4/12/2018 | 4/12/2018 |
|
| PD Weekly Public Notice | 4/17/2018 | 4/17/2018 |
|
| Final Order Issued | 6/28/2018 | 6/28/2018 |
|
| Certificate Remaining Issued | 6/28/2018 | |
RR Cert 93831 issued supersedes Cert 91580
|
| Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
| CBU Due | 10/1/2022 | 10/1/2022 |
|
| Certificate Confirming Issued | 5/30/2024 | 5/30/2024 |
CF 97773 Issued Together with Certificate 93831 Supersedes CERT 91580
|
| Final Order Issued | 5/30/2024 | 5/30/2024 |
|