Process Step | Date Initiated | Date Completed | Comments |
Received | 11/28/2016 | 11/28/2016 |
|
WMR Request | 12/1/2016 | 12/23/2016 |
|
GW Review Request | 12/1/2016 | 8/23/2017 |
|
Transfer Initial Comment Period | 12/6/2016 | 1/6/2017 |
|
Draft PD Issued | 12/13/2017 | 12/13/2017 |
|
PD Issued | 4/12/2018 | 4/12/2018 |
|
PD Weekly Public Notice | 4/17/2018 | 4/17/2018 |
|
Final Order Issued | 6/28/2018 | 6/28/2018 |
|
Certificate Remaining Issued | 6/28/2018 | |
RR Cert 93831 issued supersedes Cert 91580
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|
Certificate Confirming Issued | 5/30/2024 | 5/30/2024 |
CF 97773 Issued Together with Certificate 93831 Supersedes CERT 91580
|
Final Order Issued | 5/30/2024 | 5/30/2024 |
|