| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/21/2016 | 11/21/2016 |
|
| WMR Request | 12/1/2016 | 12/12/2016 |
|
| Transfer Initial Comment Period | 12/6/2016 | 1/6/2017 |
|
| PD Issued | 7/20/2017 | 7/20/2017 |
|
| PD Weekly Public Notice | 7/25/2017 | 7/25/2017 |
|
| Final Order Issued | 9/1/2017 | 9/1/2017 |
|
| Certificate Remaining Issued | 9/1/2017 | |
CERT 93338 ISSUED SUPERSEDES CERT 44735
|
| Extension Application Received | 9/13/2018 | 9/13/2018 |
|
| Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
| Extension FO Issued | 12/4/2018 | 12/4/2018 |
|
| CBU Due | 10/1/2019 | 10/1/2019 |
|
| Extended Completion Date [Extension C Date] | 10/1/2020 | 10/1/2020 |
|
| CBU Completeness Review | 5/28/2021 | 6/9/2021 |
|
| CBU Received | 5/28/2021 | 5/28/2021 |
|
| CBU Due | 10/1/2021 | 10/1/2021 |
|
| Certificate Confirming Issued | 2/10/2023 | 2/10/2023 |
|