| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/28/2016 | 11/28/2016 |
|
| WMR Request | 12/1/2016 | 12/2/2016 |
|
| ODFW Review | 12/1/2016 | 12/2/2016 |
|
| Transfer Initial Comment Period | 12/6/2016 | 1/6/2017 |
|
| Draft PD Issued | 1/31/2017 | |
|
| PD Issued | 3/27/2017 | 3/27/2017 |
|
| PD Weekly Public Notice | 4/4/2017 | 4/4/2017 |
|
| Final Order Issued | 5/9/2017 | 5/9/2017 |
|
| Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
| CBU Received | 11/13/2018 | 11/13/2018 |
|
| Certificate Confirming Issued | 3/8/2019 | 3/8/2019 |
|
| CBU Due | 10/1/2019 | 10/1/2019 |
|