| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/27/2016 | 12/27/2016 |
|
| WMR Request | 1/3/2017 | 2/2/2017 |
|
| GW Review Request | 1/3/2017 | 5/9/2017 |
|
| Transfer Initial Comment Period | 1/10/2017 | 2/10/2017 |
|
| Reimbursement Authority | 4/20/2017 | 8/14/2017 |
|
| RA Applicant Agreement | 4/24/2017 | 4/24/2017 |
|
| Draft PD Issued | 5/25/2017 | 5/25/2017 |
|
| PD Issued | 7/5/2017 | 7/5/2017 |
|
| PD Weekly Public Notice | 7/11/2017 | 7/11/2017 |
|
| Final Order Issued | 8/14/2017 | 8/14/2017 |
|
| Certificate Remaining Issued | 8/14/2017 | |
CERT 93306 ISSUED SUPERSEDES CERT 91929
CERT 93307 ISSUED SUPERSEDES CERT 91931
|
| Final Order Issued | 8/28/2017 | 8/28/2017 |
|
| Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
| CBU Due | 10/1/2022 | 10/1/2022 |
|
| CBU Received | 3/5/2024 | 3/5/2024 |
|
| Certificate Confirming Issued | 9/27/2024 | 9/27/2024 |
|