| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/3/2017 | 1/3/2017 |
|
| WMR Request | 1/10/2017 | 1/11/2017 |
|
| Transfer Initial Comment Period | 1/17/2017 | 2/17/2017 |
|
| PD Issued | 4/12/2017 | 4/12/2017 |
|
| PD Weekly Public Notice | 4/18/2017 | 4/18/2017 |
|
| Certificate Remaining Issued | 6/16/2017 | |
CERT 92979 ISSUED SUPERSEDES CERT 1510
|
| Final Order Issued | 6/16/2017 | 6/16/2017 |
|
| CBU Received | 3/12/2018 | 3/12/2018 |
|
| Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
| CBU Due | 10/1/2019 | 10/1/2019 |
|