Process Step | Date Initiated | Date Completed | Comments |
Received | 1/5/2017 | 1/5/2017 |
|
WMR Request | 1/10/2017 | 3/2/2017 |
|
Transfer Initial Comment Period | 1/17/2017 | 2/17/2017 |
|
Final Order Issued | 4/27/2017 | 4/27/2017 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Received | 12/21/2018 | 12/21/2018 |
|
Proof to the Satisfaction | 1/10/2019 | 1/10/2019 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|