| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/10/2017 | 1/10/2017 |
|
| WMR Request | 1/17/2017 | 1/18/2017 |
|
| GW Review Request | 1/17/2017 | 9/22/2017 |
|
| Transfer Initial Comment Period | 1/24/2017 | 2/24/2017 |
|
| Draft PD Issued | 11/15/2017 | 11/15/2017 |
|
| PD Issued | 4/25/2018 | 4/25/2018 |
|
| PD Weekly Public Notice | 5/1/2018 | 5/1/2018 |
|
| Final Order Issued | 6/21/2018 | 6/21/2018 |
|
| Certificate Remaining Issued | 6/21/2018 | |
RR Cert 93830 issued supersedes Cert 89916
|
| CBU Completeness Review | 9/4/2020 | 9/11/2020 |
|
| CBU Received | 9/4/2020 | 9/4/2020 |
|
| Certificate Confirming Issued | 10/28/2022 | 10/28/2022 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|