Process Step | Date Initiated | Date Completed | Comments |
Received | 2/21/2017 | 2/21/2017 |
|
WMR Request | 2/28/2017 | 3/15/2017 |
|
Transfer Initial Comment Period | 3/7/2017 | 4/7/2017 |
|
Draft PD Issued | 7/10/2017 | 7/10/2017 |
|
News $ Due Letter | 8/23/2017 | |
|
PD Issued | 11/3/2017 | 11/3/2017 |
|
PD Weekly Public Notice | 11/7/2017 | 11/7/2017 |
|
Final Order Issued | 2/14/2018 | 2/14/2018 |
|
Certificate Remaining Issued | 2/14/2018 | |
RR Cert 93620 issued superseded Cert 62490
|
Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
CBU Due | 10/1/2020 | 10/1/2020 |
|
Certificate Confirming Issued | 5/20/2022 | 5/20/2022 |
|