Process Step | Date Initiated | Date Completed | Comments |
Received | 3/2/2017 | 3/2/2017 |
|
WMR Request | 3/7/2017 | 3/31/2017 |
|
GW Review Request | 3/7/2017 | 11/14/2017 |
|
Transfer Initial Comment Period | 3/14/2017 | 4/14/2017 |
|
Draft PD Issued | 3/8/2018 | 3/19/2018 |
|
PD Issued | 4/12/2018 | 4/12/2018 |
|
PD Weekly Public Notice | 4/17/2018 | 4/17/2018 |
|
Final Order Issued | 6/4/2018 | 6/4/2018 |
|
CBU Received | 2/27/2019 | 2/27/2019 |
|
Certificate Confirming Issued | 6/12/2019 | 6/12/2019 |
|
Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
CBU Due | 10/1/2024 | 10/1/2024 |
|