Process Step | Date Initiated | Date Completed | Comments |
Received | 3/9/2017 | 3/9/2017 |
|
WMR Request | 3/10/2017 | 3/13/2017 |
|
Transfer Initial Comment Period | 3/14/2017 | 4/14/2017 |
|
Draft PD Issued | 6/12/2017 | 6/12/2017 |
|
PD Issued | 8/1/2017 | 8/1/2017 |
|
PD Weekly Public Notice | 8/8/2017 | 8/8/2017 |
|
Certificate Remaining Issued | 9/19/2017 | |
CERT 93347 ISSUED SUPERSEDES CERT 57784
|
Final Order Issued | 9/19/2017 | 9/19/2017 |
|
Completion Due (C Date) | 10/1/2018 | 10/1/2018 |
|
CBU Due | 10/1/2019 | 10/1/2019 |
|