Process Step | Date Initiated | Date Completed | Comments |
Received | 3/20/2017 | 3/20/2017 |
|
WMR Request | 3/22/2017 | 4/17/2017 |
|
Transfer Initial Comment Period | 3/28/2017 | 4/28/2017 |
|
Draft PD Issued | 2/8/2018 | 2/8/2018 |
|
PD Issued | 4/9/2018 | 4/9/2018 |
|
PD Weekly Public Notice | 4/10/2018 | 4/10/2018 |
|
Final Order Issued | 5/25/2018 | 5/25/2018 |
|
CBU Received | 9/9/2019 | 9/9/2019 |
|
Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
Certificate Confirming Issued | 5/26/2020 | 5/26/2020 |
|
CBU Due | 10/1/2020 | 10/1/2020 |
|