| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/27/2017 | 3/27/2017 |
|
| WMR Request | 3/30/2017 | 10/6/2017 |
|
| ODFW Review | 3/30/2017 | 10/9/2017 |
|
| Transfer Initial Comment Period | 4/4/2017 | 5/5/2017 |
|
| Draft PD Issued | 11/13/2017 | 11/13/2017 |
|
| PD Issued | 12/28/2017 | 12/28/2017 |
|
| PD Weekly Public Notice | 1/2/2018 | 1/2/2018 |
|
| Final Order Issued | 2/6/2018 | 2/6/2018 |
|
| Certificate Remaining Issued | 2/6/2018 | |
RR Cert 93601 issued superseded 35649
|
| Certificate Remaining Issued | 2/6/2018 | |
RR Cert 93600 issued superseded Cert 26393
|
| Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
| CBU Received | 10/11/2019 | 10/11/2019 |
|
| CBU Received | 10/11/2019 | 10/11/2019 |
|
| CBU Due | 10/1/2020 | 10/1/2020 |
|
| Certificate Confirming Issued | 10/15/2021 | 10/15/2021 |
|