| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/5/2017 | 4/5/2017 |
|
| Reimbursement Authority | 4/5/2017 | 9/28/2017 |
|
| WMR Request | 4/13/2017 | 4/19/2017 |
|
| Transfer Initial Comment Period | 4/18/2017 | 5/19/2017 |
|
| RA Applicant Agreement | 5/17/2017 | 5/17/2017 |
|
| Draft PD Issued | 6/12/2017 | 6/12/2017 |
|
| PD Issued | 8/7/2017 | 8/7/2017 |
|
| PD Weekly Public Notice | 8/15/2017 | 8/15/2017 |
|
| Final Order Issued | 9/28/2017 | 9/28/2017 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| Extension Application Received | 10/6/2022 | 10/6/2022 |
|
| Extension FO Issued | 10/31/2022 | 10/31/2022 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|
| Extended Completion Date [Extension C Date] | 10/1/2027 | 10/1/2027 |
|
| CBU Due | 10/1/2028 | 10/1/2028 |
|