Process Step | Date Initiated | Date Completed | Comments |
Received | 4/17/2017 | 4/17/2017 |
|
WMR Request | 4/21/2017 | 4/24/2017 |
|
Transfer Initial Comment Period | 4/25/2017 | 5/26/2017 |
|
Draft PD Issued | 6/13/2017 | 6/13/2017 |
|
PD Issued | 2/26/2018 | 2/26/2018 |
|
PD Weekly Public Notice | 2/27/2018 | 2/27/2018 |
|
Final Order Issued | 4/5/2018 | 4/5/2018 |
|
Certificate Remaining Issued | 4/5/2018 | |
RR Cert 93661 issued supersedes Cert 44466
|
Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
CBU Due | 10/1/2020 | 10/1/2020 |
|
CBU Received | 9/20/2024 | 9/20/2024 |
|