| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/18/2017 | 5/18/2017 |
|
| WMR Request | 5/24/2017 | 10/13/2017 |
|
| Transfer Initial Comment Period | 5/30/2017 | 6/30/2017 |
|
| Deficiency Letter | 3/16/2018 | 5/7/2018 |
|
| Draft PD Issued | 9/19/2018 | 9/26/2018 |
|
| PD Issued | 10/8/2018 | 10/8/2018 |
|
| PD Weekly Public Notice | 10/9/2018 | 10/9/2018 |
|
| Final Order Issued | 11/20/2018 | 11/20/2018 |
|
| Certificate Remaining Issued | 5/6/2019 | 5/6/2019 |
Certificate 94350 issued supersedes Certificate 57086
|
| CBU Received | 12/6/2019 | 12/6/2019 |
|
| Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
| CBU Due | 10/1/2021 | 10/1/2021 |
|
| Certificate Confirming Issued | 4/8/2022 | 4/8/2022 |
|