| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/23/2017 | 6/23/2017 |
|
| WMR Request | 6/26/2017 | 7/5/2017 |
|
| ODFW Review | 6/26/2017 | 7/26/2017 |
|
| Transfer Initial Comment Period | 6/27/2017 | 7/28/2017 |
|
| Draft PD Issued | 10/16/2017 | 10/16/2017 |
|
| PD Issued | 11/17/2017 | 11/17/2017 |
|
| PD Weekly Public Notice | 11/28/2017 | 11/28/2017 |
|
| Certificate Remaining Issued | 2/14/2018 | |
RR Cert 93619 issued superseded cert 45393
|
| Final Order Issued | 2/14/2018 | 2/14/2018 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|