Process Step | Date Initiated | Date Completed | Comments |
Received | 7/3/2017 | 7/3/2017 |
|
WMR Request | 7/6/2017 | 8/1/2017 |
|
GW Review Request | 7/6/2017 | 8/22/2018 |
|
Transfer Initial Comment Period | 7/11/2017 | 8/11/2017 |
|
Draft PD Issued | 12/5/2018 | 12/5/2018 |
|
News $ Due Letter | 2/1/2019 | |
|
PD Issued | 4/4/2019 | 4/4/2019 |
|
PD Weekly Public Notice | 4/9/2019 | 4/9/2019 |
|
Final Order Issued | 5/21/2019 | 5/21/2019 |
|
CBU Received | 9/16/2019 | 9/16/2019 |
|
Proposed Certificate Mailing | 7/13/2021 | 7/13/2021 |
|
Certificate Confirming Issued | 11/19/2021 | 11/19/2021 |
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|