Process Step | Date Initiated | Date Completed | Comments |
Received | 7/20/2017 | 7/20/2017 |
|
WMR Request | 7/21/2017 | 8/10/2017 |
|
GW Review Request | 7/21/2017 | 11/27/2017 |
|
Transfer Initial Comment Period | 7/25/2017 | 8/25/2017 |
|
GW Review Request | 12/21/2017 | 12/21/2017 |
|
Reimbursement Authority | 2/15/2018 | 6/18/2018 |
|
RA Applicant Agreement | 2/22/2018 | 2/22/2018 |
|
Draft PD Issued | 3/20/2018 | 3/20/2018 |
|
PD Issued | 4/23/2018 | 4/23/2018 |
|
PD Weekly Public Notice | 4/24/2018 | 4/24/2018 |
|
Final Order Issued | 6/18/2018 | 6/18/2018 |
|
Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|