Process Step | Date Initiated | Date Completed | Comments |
Received | 9/8/2017 | 9/8/2017 |
|
Reimbursement Authority | 9/8/2017 | 6/21/2018 |
|
WMR Request | 9/11/2017 | 11/30/2017 |
|
Transfer Initial Comment Period | 9/12/2017 | 10/13/2017 |
|
GW Review Request | 9/14/2017 | 11/16/2017 |
|
RA Applicant Agreement | 10/18/2017 | 10/18/2017 |
|
Draft PD Issued | 1/11/2018 | 1/11/2018 |
|
PD Issued | 2/26/2018 | 2/26/2018 |
|
PD Weekly Public Notice | 2/27/2018 | 2/27/2018 |
|
Certificate Remaining Issued | 6/21/2018 | |
RR Cert 93816 issued supersedes Cert 57754
|
Final Order Issued | 6/21/2018 | 6/21/2018 |
|
Completion Due (C Date) | 10/1/2027 | 10/1/2027 |
|
CBU Due | 10/1/2028 | 10/1/2028 |
|