Process Step | Date Initiated | Date Completed | Comments |
Received | 9/7/2017 | 9/7/2017 |
|
WMR Request | 9/11/2017 | 12/4/2020 |
|
Transfer Initial Comment Period | 9/12/2017 | 10/13/2017 |
|
Deficiency Letter | 12/7/2020 | 1/25/2021 |
|
Draft PD Issued | 2/17/2021 | 6/14/2021 |
|
PD Issued | 4/22/2021 | 4/22/2021 |
|
PD Weekly Public Notice | 4/27/2021 | 4/27/2021 |
|
Certificate Remaining Issued | 6/14/2021 | 6/14/2021 |
RR Cert 95644 Issued supersedes Cet 93271
|
Final Order Issued | 6/14/2021 | 6/14/2021 |
|
CBU Completeness Review | 10/12/2021 | 10/20/2021 |
|
CBU Received | 10/12/2021 | 10/12/2021 |
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
Certificate Confirming Issued | 1/27/2023 | 1/27/2023 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|