| Process Step | Date Initiated | Date Completed | Comments |
| Received | 9/14/2017 | 9/14/2017 |
|
| WMR Request | 9/15/2017 | 9/19/2017 |
|
| GW Review Request | 9/15/2017 | 3/30/2018 |
|
| Transfer Initial Comment Period | 9/19/2017 | 10/20/2017 |
|
| Draft PD Issued | 9/20/2019 | 10/11/2019 |
|
| News $ Due Letter | 10/29/2019 | 10/31/2019 |
|
| PD Weekly Public Notice | 11/19/2019 | 11/19/2019 |
|
| PD Issued | 11/19/2019 | 11/19/2019 |
|
| Final Order Issued | 1/15/2020 | 1/15/2020 |
|
| Certificate Remaining Issued | 1/15/2020 | 1/15/2020 |
RR Cert 94701 Issued Supersedes Cert 80997
|
| Certificate Remaining Issued | 1/15/2020 | 1/15/2020 |
RR Cert 94702 Issued Supersedes Cert 80998
|
| CBU Completeness Review | 9/13/2021 | 9/24/2021 |
|
| CBU Received | 9/13/2021 | 9/13/2021 |
|
| Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
| CBU Due | 10/1/2022 | 10/1/2022 |
|
| Certificate Confirming Issued | 6/19/2023 | 6/19/2023 |
|