| Process Step | Date Initiated | Date Completed | Comments |
| Received | 10/10/2017 | 10/10/2017 |
|
| WMR Request | 10/12/2017 | 10/17/2017 |
|
| ODFW Review | 10/12/2017 | 10/20/2017 |
|
| Transfer Initial Comment Period | 10/17/2017 | 11/17/2017 |
|
| Draft PD Issued | 1/18/2018 | 1/18/2018 |
|
| PD Issued | 4/5/2018 | 4/5/2018 |
|
| PD Weekly Public Notice | 4/10/2018 | 4/10/2018 |
|
| Certificate Remaining Issued | 6/4/2018 | |
RR Cert 93698 issued supersedes Cert 4754
RR Cert 93699 issued supersedes Cert 4772
|
| Final Order Issued | 6/4/2018 | 6/4/2018 |
|
| Completion Due (C Date) | 10/1/2023 | 10/1/2023 |
|
| CBU Due | 10/1/2024 | 10/1/2024 |
|