| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/29/2017 | 11/29/2017 |
|
| GW Review Request | 12/1/2017 | 9/7/2018 |
|
| WMR Request | 12/1/2017 | 1/25/2018 |
|
| Transfer Initial Comment Period | 12/5/2017 | 1/5/2018 |
|
| Permit Superseding Issued | 1/2/2019 | 1/2/2019 |
Permit G-18130 Issued Supersedes Permit G-14063
|
| Final Order Issued | 1/2/2019 | 1/2/2019 |
|