Process Step | Date Initiated | Date Completed | Comments |
Received | 12/11/2017 | 12/11/2017 |
|
GW Review Request | 12/15/2017 | 3/20/2018 |
|
WMR Request | 12/15/2017 | 3/22/2018 |
|
Transfer Initial Comment Period | 12/19/2017 | 1/19/2018 |
|
Deficiency Letter | 4/3/2018 | 5/14/2018 |
|
Draft PD Issued | 5/30/2018 | 6/15/2018 |
|
PD Issued | 6/28/2018 | 6/28/2018 |
|
PD Weekly Public Notice | 7/3/2018 | 7/3/2018 |
|
Final Order Issued | 8/14/2018 | 8/14/2018 |
|
Certificate Remaining Issued | 8/14/2018 | 8/14/2018 |
|
Certificate Remaining Issued | 8/14/2018 | 8/14/2018 |
|
CBU Received | 12/20/2018 | 12/20/2018 |
|
Certificate Confirming Issued | 4/25/2019 | 4/25/2019 |
|
Certificate Confirming Issued | 4/25/2019 | 4/25/2019 |
|
Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
CBU Due | 10/1/2023 | 10/1/2023 |
|