Process Step | Date Initiated | Date Completed | Comments |
Received | 1/16/2018 | 1/16/2018 |
|
Transfer Initial Comment Period | 1/16/2018 | 2/16/2018 |
|
WMR Request | 1/16/2018 | 1/18/2018 |
|
Certificate Remaining Issued | 11/19/2018 | 11/19/2018 |
RR 94111 Issued Supersedes Cert 91246
|
Final Order Issued | 11/19/2018 | 11/19/2018 |
|
Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|