| Process Step | Date Initiated | Date Completed | Comments |
| Received | 1/29/2018 | 1/29/2018 |
|
| WMR Request | 2/2/2018 | 2/26/2018 |
|
| GW Review Request | 2/2/2018 | 6/4/2018 |
|
| Transfer Initial Comment Period | 2/6/2018 | 3/9/2018 |
|
| Reimbursement Authority | 4/26/2019 | 5/22/2019 |
|
| Reimbursement Authority | 5/23/2019 | 10/22/2019 |
|
| RA Applicant Agreement | 5/28/2019 | 5/28/2019 |
|
| PD Issued | 9/23/2019 | 9/23/2019 |
|
| PD Weekly Public Notice | 9/24/2019 | 9/24/2019 |
|
| Certificate Remaining Issued | 12/18/2019 | 12/18/2019 |
RR 94472 Issued Supersedes Cert 93424
|
| Final Order Issued | 12/18/2019 | 12/18/2019 |
|
| Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
| CBU Received | 12/5/2024 | 12/5/2024 |
|
| CBU Due | 10/1/2025 | 10/1/2025 |
|