| Process Step | Date Initiated | Date Completed | Comments |
| RA Applicant Agreement | 2/5/2018 | 7/13/2018 |
|
| Received | 2/5/2018 | 2/5/2018 |
|
| WMR Request | 2/9/2018 | 2/14/2018 |
|
| Transfer Initial Comment Period | 2/13/2018 | 3/16/2018 |
|
| RA Applicant Agreement | 2/22/2018 | 2/22/2018 |
|
| Draft PD Issued | 3/20/2018 | 3/20/2018 |
|
| PD Issued | 5/21/2018 | 5/21/2018 |
|
| PD Weekly Public Notice | 5/22/2018 | 5/22/2018 |
|
| Final Order Issued | 7/13/2018 | 7/13/2018 |
|
| Certificate Remaining Issued | 7/13/2018 | |
RR Cert 93861 issued supersedes Cert 81168
|
| Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
| CBU Completeness Review | 8/26/2020 | 9/3/2020 |
|
| CBU Received | 8/26/2020 | 8/26/2020 |
|
| CBU Due | 10/1/2020 | 10/1/2020 |
|
| Certificate Confirming Issued | 3/10/2023 | 3/10/2023 |
|