Process Step | Date Initiated | Date Completed | Comments |
Received | 2/28/2018 | 2/28/2018 |
|
GW Review Request | 3/2/2018 | 4/30/2018 |
|
WMR Request | 3/2/2018 | 3/12/2018 |
|
Transfer Initial Comment Period | 3/6/2018 | 4/6/2018 |
|
Draft PD Issued | 6/26/2018 | 6/26/2018 |
|
PD Issued | 7/23/2018 | 7/23/2018 |
|
PD Weekly Public Notice | 7/24/2018 | 7/24/2018 |
|
Final Order Issued | 8/29/2018 | 8/29/2018 |
|
Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
CBU Completeness Review | 9/28/2020 | 10/1/2020 |
|
CBU Received | 9/28/2020 | 9/28/2020 |
|
CBU Due | 10/1/2020 | 10/1/2020 |
|
Proposed Certificate Mailing | 4/28/2023 | 7/2/2023 |
|
Extension Application Received | 7/14/2023 | 7/14/2023 |
|
Extension FO Issued | 7/25/2023 | 7/25/2023 |
|
Certificate Confirming Issued | 11/3/2023 | 11/3/2023 |
|
Extended Completion Date [Extension C Date] | 10/1/2024 | 10/1/2024 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|