Process Step | Date Initiated | Date Completed | Comments |
Received | 4/10/2018 | 4/10/2018 |
|
WMR Request | 4/11/2018 | 4/12/2018 |
|
Transfer Initial Comment Period | 4/17/2018 | 5/17/2018 |
|
PD Issued | 4/4/2019 | 4/4/2019 |
|
PD Weekly Public Notice | 4/9/2019 | 4/9/2019 |
|
Certificate Remaining Issued | 6/3/2019 | 6/3/2019 |
RR 94404 Issued Supersedes Cert 80060
|
Certificate Remaining Issued | 6/3/2019 | 6/3/2019 |
RR 94405 Issued Supersedes Cert 80061
|
Final Order Issued | 6/3/2019 | 6/3/2019 |
|
CBU Received | 3/2/2020 | 3/2/2020 |
|
Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|
Proposed Certificate Mailing | 9/24/2024 | 9/24/2024 |
|