Process Step | Date Initiated | Date Completed | Comments |
Received | 6/8/2018 | 6/8/2018 |
|
WMR Request | 6/13/2018 | 7/2/2018 |
|
GW Review Request | 6/13/2018 | 2/19/2019 |
|
Transfer Initial Comment Period | 6/19/2018 | 7/19/2018 |
|
Draft PD Issued | 6/28/2019 | 7/31/2019 |
|
News $ Due Letter | 9/10/2019 | 9/13/2019 |
|
PD Issued | 9/19/2019 | 9/19/2019 |
|
PD Weekly Public Notice | 9/24/2019 | 9/24/2019 |
|
Certificate Remaining Issued | 12/4/2019 | 12/4/2019 |
RR Certificate 94559 issued supersedes Cert 36301
|
Final Order Issued | 12/4/2019 | 12/4/2019 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|