Process Step | Date Initiated | Date Completed | Comments |
Received | 6/8/2018 | 6/8/2018 |
|
WMR Request | 6/13/2018 | 7/11/2018 |
|
Transfer Initial Comment Period | 6/19/2018 | 7/19/2018 |
|
Final Order Issued | 8/29/2018 | 8/29/2018 |
|
Completion Due (C Date) | 10/1/2019 | 10/1/2019 |
|
Extension Application Received | 10/2/2019 | 10/2/2019 |
|
Extension FO Issued | 12/13/2019 | 12/13/2019 |
|
CBU Received | 8/5/2020 | 8/5/2020 |
|
Proof to the Satisfaction | 9/3/2020 | 9/3/2020 |
|
CBU Due | 10/1/2020 | 10/1/2020 |
|
Extended Completion Date [Extension C Date] | 10/1/2020 | 10/1/2020 |
|
CBU Due | 10/1/2021 | 10/1/2021 |
|