Process Step | Date Initiated | Date Completed | Comments |
Received | 6/11/2018 | 6/11/2018 |
|
Reimbursement Authority | 6/11/2018 | |
|
WMR Request | 6/13/2018 | 6/28/2018 |
|
GW Review Request | 6/13/2018 | 7/19/2018 |
|
Transfer Initial Comment Period | 6/19/2018 | 7/19/2018 |
|
RA Applicant Agreement | 6/26/2018 | 6/26/2018 |
|
Draft PD Issued | 8/20/2018 | 9/10/2018 |
|
News $ Due Letter | 9/26/2018 | 10/1/2018 |
|
PD Issued | 10/8/2018 | 10/8/2018 |
|
PD Weekly Public Notice | 10/9/2018 | 10/9/2018 |
|
Final Order Issued | 11/28/2018 | 11/28/2018 |
|
Certificate Remaining Issued | 12/13/2018 | 12/13/2018 |
RR 94176 Issued Supersedes Cert 91569
|
CBU Received | 9/21/2021 | 9/21/2021 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|
Proposed Certificate Mailing | 7/3/2023 | 7/3/2023 |
|
Certificate Confirming Issued | 10/6/2023 | 10/6/2023 |
|