| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/28/2018 | 6/28/2018 |
|
| WMR Request | 7/2/2018 | 8/1/2018 |
|
| Transfer Initial Comment Period | 7/3/2018 | 8/2/2018 |
|
| Draft PD Issued | 5/28/2019 | 5/28/2019 |
|
| PD Issued | 11/25/2019 | 11/25/2019 |
|
| PD Weekly Public Notice | 11/26/2019 | 11/26/2019 |
|
| Final Order Issued | 1/13/2020 | 1/13/2020 |
|
| Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
| CBU Due | 10/1/2022 | 10/1/2022 |
|
| CBU Received | 12/5/2023 | 12/5/2023 |
|
| Certificate Confirming Issued | 4/1/2025 | 4/1/2025 |
|