| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/12/2018 | 7/12/2018 |
|
| WMR Request | 7/13/2018 | 8/27/2018 |
|
| GW Review Request | 7/13/2018 | 5/29/2019 |
|
| Transfer Initial Comment Period | 7/17/2018 | 8/16/2018 |
|
| GW Review Request | 5/29/2019 | 6/25/2019 |
|
| Draft PD Issued | 9/16/2019 | 10/12/2019 |
|
| News $ Due Letter | 10/29/2019 | 11/7/2019 |
|
| PD Weekly Public Notice | 11/19/2019 | 11/19/2019 |
|
| PD Issued | 11/19/2019 | 11/19/2019 |
|
| Final Order Issued | 1/13/2020 | 1/13/2020 |
|
| Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
| CBU Received | 2/16/2022 | 2/16/2022 |
|
| CBU Due | 10/1/2022 | 10/1/2022 |
|
| Certificate Confirming Issued | 8/11/2023 | 8/11/2023 |
|