| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/12/2018 | 7/12/2018 |
|
| WMR Request | 7/13/2018 | 7/28/2018 |
|
| Transfer Initial Comment Period | 7/17/2018 | 8/16/2018 |
|
| PD Issued | 6/21/2019 | 6/21/2019 |
|
| PD Weekly Public Notice | 6/25/2019 | 6/25/2019 |
|
| Final Order Issued | 9/19/2019 | 9/19/2019 |
|
| CBU Completeness Review | 6/21/2021 | 7/7/2021 |
|
| CBU Received | 6/21/2021 | 6/21/2021 |
|
| Certificate Confirming Issued | 2/10/2023 | 2/10/2023 |
|