Process Step | Date Initiated | Date Completed | Comments |
Received | 7/12/2018 | 7/12/2018 |
|
WMR Request | 7/13/2018 | 7/30/2018 |
|
GW Review Request | 7/13/2018 | 4/2/2019 |
|
Transfer Initial Comment Period | 7/17/2018 | 8/16/2018 |
|
Draft PD Issued | 9/12/2019 | 10/8/2019 |
|
News $ Due Letter | 11/4/2019 | 11/4/2019 |
|
PD Weekly Public Notice | 11/19/2019 | 11/19/2019 |
|
PD Issued | 11/19/2019 | 11/19/2019 |
|
Final Order Issued | 1/15/2020 | 1/15/2020 |
|
Certificate Remaining Issued | 1/15/2020 | 1/15/2020 |
RR Cert 94703 Issued Supercedes Cert 63600
|
CBU Received | 1/21/2022 | 1/21/2022 |
|
Certificate Confirming Issued | 10/28/2022 | 10/28/2022 |
|
Completion Due (C Date) | 10/1/2025 | 10/1/2025 |
|
CBU Due | 10/1/2026 | 10/1/2026 |
|