| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/23/2018 | 7/23/2018 |
|
| WMR Request | 7/26/2018 | 2/19/2019 |
|
| Transfer Initial Comment Period | 7/31/2018 | 8/30/2018 |
|
| Certificate Remaining Issued | 6/30/2021 | 6/30/2021 |
RR Cert 94966 Issued supersedes Cert 93497
|
| Final Order Issued | 6/30/2021 | 6/30/2021 |
|
| Certificate Confirming Issued | 6/30/2021 | 6/30/2021 |
CF Cert 94965 Issued supersedes Cert 87729
|
| CBU Completeness Review | 11/4/2021 | 11/15/2021 |
|
| CBU Received | 11/4/2021 | 11/4/2021 |
|
| Completion Due (C Date) | 10/1/2022 | 10/1/2022 |
|
| CBU Due | 10/1/2023 | 10/1/2023 |
|