| Process Step | Date Initiated | Date Completed | Comments |
| Received | 8/2/2018 | 8/2/2018 |
|
| WMR Request | 8/2/2018 | 8/27/2018 |
|
| Transfer Initial Comment Period | 8/7/2018 | 9/6/2018 |
|
| Draft PD Issued | 9/24/2019 | 9/27/2019 |
|
| PD Issued | 10/23/2019 | 10/23/2019 |
|
| PD Weekly Public Notice | 10/29/2019 | 10/29/2019 |
|
| Certificate Remaining Issued | 1/2/2020 | 1/2/2020 |
RR Cert 94676 Issued Supersedes Permit 33129
|
| Final Order Issued | 1/2/2020 | 1/2/2020 |
|
| CBU Received | 2/11/2021 | 2/11/2021 |
|
| Certificate Confirming Issued | 5/18/2021 | 5/18/2021 |
|
| Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
| CBU Due | 10/1/2025 | 10/1/2025 |
|