Process Step | Date Initiated | Date Completed | Comments |
Received | 7/27/2018 | 7/27/2018 |
|
ODFW Review | 8/1/2018 | 8/20/2018 |
|
WMR Request | 8/1/2018 | 8/21/2018 |
|
Transfer Initial Comment Period | 8/7/2018 | 9/6/2018 |
|
Certificate Confirming Issued | 5/16/2019 | 5/16/2019 |
CF 94347 Issued Supersedes Cert 3091
|
Certificate Remaining Issued | 5/16/2019 | 5/16/2019 |
RR 94348 Issued Supersedes Cert 3091
|
Final Order Issued | 5/16/2019 | 5/16/2019 |
|