| Process Step | Date Initiated | Date Completed | Comments |
| Received | 8/14/2018 | 8/14/2018 |
|
| Reimbursement Authority | 8/14/2018 | |
|
| WMR Request | 8/16/2018 | 9/17/2018 |
|
| Transfer Initial Comment Period | 8/21/2018 | 9/20/2018 |
|
| RA Applicant Agreement | 9/4/2018 | 9/4/2018 |
|
| Draft PD Issued | 10/15/2018 | |
|
| PD Issued | 12/17/2018 | 12/17/2018 |
|
| PD Weekly Public Notice | 12/18/2018 | 12/18/2018 |
|
| Certificate Remaining Issued | 1/30/2019 | 1/30/2019 |
RR 94220 Issued Supercedes Cert 91306
|
| Final Order Issued | 1/30/2019 | 1/30/2019 |
|
| Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
| CBU Due | 10/1/2021 | 10/1/2021 |
|