Process Step | Date Initiated | Date Completed | Comments |
Received | 9/13/2018 | 9/13/2018 |
|
Reimbursement Authority | 9/13/2018 | |
|
WMR Request | 9/17/2018 | 10/17/2018 |
|
GW Review Request | 9/17/2018 | 9/17/2018 |
|
ODFW Review | 9/17/2018 | 3/12/2019 |
|
Transfer Initial Comment Period | 9/18/2018 | 10/18/2018 |
|
RA Applicant Agreement | 10/5/2018 | 10/5/2018 |
|
Deficiency Letter | 10/8/2018 | 10/17/2018 |
|
Draft PD Issued | 3/27/2019 | 4/30/2019 |
|
Deficiency Letter | 4/26/2019 | 4/30/2019 |
|
News $ Due Letter | 5/22/2019 | 5/31/2019 |
|
PD Issued | 6/10/2019 | 6/10/2019 |
|
PD Weekly Public Notice | 6/11/2019 | 6/11/2019 |
|
Final Order Issued | 7/24/2019 | 7/24/2019 |
|
CBU Received | 1/8/2020 | 1/8/2020 |
|
Certificate Confirming Issued | 7/29/2022 | 7/29/2022 |
|