| Process Step | Date Initiated | Date Completed | Comments |
| Received | 10/15/2018 | 10/15/2018 |
|
| WMR Request | 10/18/2018 | 10/19/2018 |
|
| GW Review Request | 10/18/2018 | 11/28/2018 |
|
| Transfer Initial Comment Period | 10/23/2018 | 11/22/2018 |
|
| Reimbursement Authority | 10/29/2018 | |
|
| RA Applicant Agreement | 11/14/2018 | 11/14/2018 |
|
| Deficiency Letter | 12/6/2018 | 12/7/2018 |
|
| Draft PD Issued | 1/3/2019 | 1/22/2019 |
|
| News $ Due Letter | 2/5/2019 | 2/8/2019 |
|
| PD Issued | 2/15/2019 | 2/15/2019 |
|
| PD Weekly Public Notice | 2/19/2019 | 2/19/2019 |
|
| Certificate Remaining Issued | 3/29/2019 | 3/29/2019 |
RR Certificate Issued 94314
|
| Final Order Issued | 3/29/2019 | 3/29/2019 |
|
| Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
| CBU Received | 4/22/2026 | 4/22/2026 |
|