Process Step | Date Initiated | Date Completed | Comments |
Received | 10/24/2018 | 10/24/2018 |
|
WMR Request | 10/26/2018 | 11/2/2018 |
|
GW Review Request | 10/26/2018 | 6/10/2019 |
|
Transfer Initial Comment Period | 10/30/2018 | 11/29/2018 |
|
Draft PD Issued | 9/12/2019 | 9/12/2019 |
|
PD Issued | 10/28/2019 | 10/28/2019 |
|
PD Weekly Public Notice | 10/29/2019 | 10/29/2019 |
|
Final Order Issued | 12/31/2019 | 12/31/2019 |
|
CBU Received | 2/28/2020 | 2/28/2020 |
|
Certificate Confirming Issued | 5/26/2020 | 5/26/2020 |
|
Completion Due (C Date) | 10/1/2021 | 10/1/2021 |
|
CBU Due | 10/1/2022 | 10/1/2022 |
|