Process Step | Date Initiated | Date Completed | Comments |
Received | 10/26/2018 | 10/26/2018 |
|
WMR Request | 10/29/2018 | 11/20/2018 |
|
Transfer Initial Comment Period | 10/30/2018 | 11/29/2018 |
|
Draft PD Issued | 10/30/2019 | 11/1/2019 |
|
PD Issued | 12/2/2019 | 12/2/2019 |
|
PD Weekly Public Notice | 12/3/2019 | 12/3/2019 |
|
Final Order Issued | 1/14/2020 | 1/14/2020 |
|
Certificate Remaining Issued | 1/14/2020 | 1/14/2020 |
RR Cert 94706 Issued Supersedes 53767 cert.
|
Certificate Remaining Issued | 1/14/2020 | 1/14/2020 |
Cert 94705 Issued Supersedes Cert 23029
|
Completion Due (C Date) | 10/1/2024 | 10/1/2024 |
|
CBU Due | 10/1/2025 | 10/1/2025 |
|