| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/3/2018 | 12/3/2018 |
|
| GW Review Request | 12/6/2018 | 5/30/2019 |
|
| Transfer Initial Comment Period | 12/11/2018 | 1/10/2019 |
|
| WMR Request | 12/11/2018 | 4/29/2019 |
|
| Deficiency Letter | 9/5/2019 | 9/5/2019 |
|
| Final Order Issued | 12/13/2019 | 12/13/2019 |
|
| Certificate Confirming Issued | 4/17/2026 | 4/17/2026 |
|